Construction is to begin next month on Brandon’s new Daly Overpass, and the prep work is beginning – this from Manitoba Transportation and Infrastructure.
Starting today (Feb 22) to July 1, 2022 – McDonald Avenue and Stickney Avenue will be closed to vehicular traffic between 17th St N and 19th St N. (See map below)
Construction, including piling activity, in this area is expected to begin in March 2022 and will last for up to a month; noise and vibration can be expected generally between 7 AM and 7 PM daily.
Sewer work will take place during the same period. While sewer and water service will continue uninterrupted, residents and business owners may occasionally experience discoloured water. Discolouration of water occurs due to changes in flow, but does not impact safety or potability of the water.

(Image – submitted)
For a list of updates, please visit www.brandon.ca/daly-overpass
The project website can be found here: https://www.gov.mb.ca/mit/wms/structures/daly_overpass/